Restoring an Electronic Document Management System (EDMS) after a failure requires coordination between infrastructure owners, application configuration, and workflows. IQusion IT LLC (IQusion) publicly describes EDMS implementation, and SL Global Service describes infrastructure and disaster recovery services. These descriptions do not define their contractual roles in a specific recovery. Effective recovery depends not only on technical implementation but also on agreed-upon acceptance criteria and decisions to return the service to users. This guide outlines key aspects to consider for verifying recovered data and EDMS functionality. This is a proposed editorial scheme that the customer should adapt to their own plan.
Separation of responsibility and recovery goals
The first step is a clear definition of roles and responsibilities. The infrastructure team is typically the owner of infrastructure recovery and is responsible for restoring base components: operating systems, databases, file storage, and network services, according to infrastructure engineering management. A separate owner for EDMS configuration recovery is appointed: routes, signing, and integrations. This can be an internal or engaged team, if such responsibility is agreed upon. It is important to agree in advance on RTO (Recovery Time Objective) goals—the target time to restore the agreed service, and RPO (Recovery Point Objective)—the maximum allowable data loss interval. These metrics must be realistic and documented in relevant agreements. 04
Infrastructure recovery: basic checks
After restoring infrastructure components, a series of basic checks must be performed. This includes confirming server availability, database performance, integrity of file systems where document attachments are stored, and the correctness of network settings. Checking backups is a key part of this stage. SL Global Service, for example, emphasizes the importance of preparing for recovery before an incident occurs, including recovery classes, isolated copies, and measurable recovery tests. Public descriptions outline claimed service directions and do not appoint the recovery executor or the person who accepts it.
EDMS application acceptance: functional verification
After successful infrastructure recovery, the application acceptance stage begins, where the customer-appointed application team verifies the EDMS operation. The results show readiness within the performed checks; sampling documents does not prove the integrity of all data. Document management implementation by IQusion includes configuring the EDMS for institutional processes, which requires thorough verification of all these settings after recovery.
EDMS post-recovery checklist
- System access: Verification of login capability for different user roles (administrator, manager, executor), as well as verification of the absence of access to restricted records for roles that do not have such rights.
- Document integrity: Selective review of documents created before the failure, verification of their content, attachments, and metadata. It is important to verify the identity of document versions and attachments, as well as the correctness of links between them.
- Approval routes: Running a test document through a standard route to confirm the correctness of stage progression, QES (Qualified Electronic Signature) signing, and task execution.
- Search and filtering: Verification of search functionality by keywords, dates, statuses, and other document attributes.
- Integrations: If the EDMS is integrated with other systems (e.g., state registries or accounting systems), it is necessary to verify the correctness of data exchange and the integrity of message queues, as well as confirmation of their processing.
- Audit logs: Verification of the presence and integrity of user action logs and system events.
- Pending approvals: Assessment of the status of documents that were in the approval process at the time of the failure, and confirmation of the ability to continue them.
Training scenario: EDMS recovery verification plan
This is a training plan, not a completed test report. The role names in the table are proposed for coordination. For interrupted exchanges, sent, confirmed, and unconfirmed messages are reconciled; a retry is allowed only after checking for possible prior execution.
| Check | Expected result | Evidence | Decision maker |
|---|---|---|---|
| Administrator access | Administrator logs into the system successfully. | Login log, interface screenshot. | Infrastructure recovery owner |
| User access (selective) | User logs in successfully, sees their documents. | Login log, screenshot of the user workspace. | EDMS configuration owner |
| Negative access check | User cannot read restricted records. | Role, resource, attempted operation and server denial; log where available. A screenshot alone is insufficient. | EDMS configuration owner |
| Viewing an old document with attachment and version | Document opens, attachment is available, version matches the selected recovery point. | Opened document, opened attachment, comparison with trusted pre-incident checksums for the same attachment versions, when available. | EDMS configuration owner |
| Creating a new document | New document is created and saved. | Created document in the system. | Process owner authorizing recovery |
| Running a test approval route | Document passes all route stages, is signed with QES. | Route log, status "Approved". | Process owner authorizing recovery |
| Searching for a document by keyword | Search returns correct results. | Search results. | EDMS configuration owner |
| Integration check (e.g., with mail) and queue | Test message is sent/received, message queue is reconciled. | Integration log, received message, queue status report with confirmations. | Infrastructure recovery owner / EDMS configuration owner |
If reference checksums are unavailable, check the attachment version, size and readability, and record that checksum-based integrity remains unverified.
Decision to return service to users
The decision to return the EDMS to users is made by the customer in accordance with their internal operational plan, after successfully passing all critical checks. Record the actual recovery time and data recovery point against RTO/RPO, identified deviations and the authorized owner’s decision. Exceeding the RTO target does not by itself mean the service must remain unavailable; the agreed operating plan governs its return. The process owner tells users when access resumes and explains any temporary restrictions.